Control register

Risks and Issues

Keep active delivery threats visible with named owners, due dates, and mitigation actions.

Register

RiskMediumResolved

Permit resubmittal review could affect mobilization

Project

Riverside Medical Office Buildout

Owner

Maya Chen

Due date

May 17, 2026

Mitigation / action

Maintain direct reviewer coordination and pre-validate all comment responses.

IssueCriticalClosed

Repeated fall-protection observation at mezzanine edge

Project

Northgate Distribution Center

Owner

Chris Jones

Due date

Jul 9, 2026

Mitigation / action

Stop work, retrain the crew, add engineered protection, and verify closeout with the safety director.

RiskHighOpen

Dock equipment upgrade exceeds current allowance

Project

Northgate Distribution Center

Owner

Lena Ortiz

Due date

Jul 15, 2026

Mitigation / action

Compare lifecycle value, validate the cost split, and decide before the vendor quote expires.

IssueCriticalOpen

Sprinkler redesign is blocking fabrication and overhead rough-in

Project

Northgate Distribution Center

Owner

Maya Chen

Due date

Jul 15, 2026

Mitigation / action

Lock insurer criteria, obtain the engineer seal, and authorize expedited fabrication.

IssueCriticalOpen

Phase 2 above-ceiling inspection failed

Project

Riverside Medical Office Buildout

Owner

Chris Jones

Due date

Jul 16, 2026

Mitigation / action

Complete firestopping corrections, upload photo evidence, and secure the earliest reinspection slot.

RiskHighMitigating

Steel productivity remained below recovery assumption

Project

Northgate Distribution Center

Owner

Aisha Rahman

Due date

Jul 18, 2026

Mitigation / action

Carry verified production rates into the recovery schedule and retain the second crew for detailing.

IssueMediumMitigating

Elevator certification retest may delay owner turnover

Project

Harbor Point Multifamily Turnover

Owner

Rita Alvarez

Due date

Jul 23, 2026

Mitigation / action

Close retest prerequisites and hold the inspector appointment with daily vendor confirmation.

RiskHighMitigating

Switchgear lead time threatens planned energization

Project

Riverside Medical Office Buildout

Owner

Daniel Brooks

Due date

Jul 26, 2026

Mitigation / action

Protect the production slot, approve the revised submittal, and track vendor milestones weekly.

RiskLowMitigating

Cost-code definitions are inconsistent across active projects

Project

Project Controls Standardization

Owner

Lena Ortiz

Due date

Jul 28, 2026

Mitigation / action

Publish a mapping table and validate forecast categories during dashboard pilot review.

RiskMediumOpen

Project teams may treat standard controls as extra administration

Project

Project Controls Standardization

Owner

Sam Rivera

Due date

Aug 4, 2026

Mitigation / action

Use pilot feedback, reduce duplicate entry, and demonstrate decisions enabled by the weekly controls.

RiskLowAccepted

Landscaping replacement may extend beyond turnover

Project

Harbor Point Multifamily Turnover

Owner

Noah Kim

Due date

Aug 7, 2026

Mitigation / action

Complete life-safety access now and schedule final planting in the approved seasonal window.