Project detail
Riverside Medical Office Buildout
Deliver a 42,000-square-foot occupied medical office buildout, including phased MEP coordination, inspections, commissioning, and tenant turnover.
Project overview
Percent complete
58%
Weekly health snapshot
Current pulse
Needs attention
Week ending Jul 19, 2026
Based on the latest submitted weekly report.
Blocked tasks
1
Overdue tasks
1
Open risks / issues
2
Executive summary
Coordination progress was strong this week, but the failed inspection and switchgear release keep the project Yellow until both constraints are cleared.
Completed this week
Next week plan
Risks / issues
Decisions needed
Tasks
Publish commissioning and turnover plan
Sam Rivera · Jul 29, 2026 to Aug 28, 2026 · 20 hrs
Depends on: Release electrical switchgear for fabrication, Pass above-ceiling inspection in Phase 2
Sequence functional testing, training, O&M delivery, and owner acceptance by floor.
Attachments
Files attached here also appear in Project Documents.
Pass above-ceiling inspection in Phase 2
Chris Jones · Jul 2, 2026 to Jul 12, 2026 · 12 hrs
Inspection cannot be rebooked until firestopping corrections and photo documentation are accepted.
Attachments
Files attached here also appear in Project Documents.
Release electrical switchgear for fabrication
Daniel Brooks · Jun 24, 2026 to Jul 26, 2026 · 16 hrs
Depends on: Complete MEP coordination clash review
Vendor has reserved a production slot pending final engineer approval of the revised submittal.
Attachments
Files attached here also appear in Project Documents.
Complete MEP coordination clash review
Maya Chen · Jun 16, 2026 to Jul 11, 2026 · 18 hrs
Depends on: Close permit coordination package
Final model review closed 31 clashes and issued coordinated ceiling-zone drawings.
Attachments
Files attached here also appear in Project Documents.
Close permit coordination package
Chris Jones · Apr 13, 2026 to May 13, 2026 · 24 hrs
Permit comments, architect responses, and jurisdiction resubmittal are complete.
Attachments
Files attached here also appear in Project Documents.
Risks and issues
Permit resubmittal review could affect mobilization
Owner: Maya Chen
Maintain direct reviewer coordination and pre-validate all comment responses.
Phase 2 above-ceiling inspection failed
Owner: Chris Jones
Complete firestopping corrections, upload photo evidence, and secure the earliest reinspection slot.
Switchgear lead time threatens planned energization
Owner: Daniel Brooks
Protect the production slot, approve the revised submittal, and track vendor milestones weekly.