Project detail
Harbor Point Multifamily Turnover
Complete quality walks, punch resolution, elevator certification, owner turnover, and warranty mobilization for a 168-unit multifamily project.
Project overview
Percent complete
82%
Weekly health snapshot
Current pulse
Needs attention
Week ending Jul 19, 2026
Based on the latest submitted weekly report.
Blocked tasks
0
Overdue tasks
0
Open risks / issues
2
Executive summary
Harbor Point remains Green. Unit punch is moving as planned, and elevator certification is the only material turnover dependency.
Completed this week
Next week plan
Risks / issues
Decisions needed
Tasks
Launch 30-day warranty review
Noah Kim · Aug 7, 2026 to Aug 15, 2026 · 6 hrs
Depends on: Issue owner turnover package
Confirm owner contacts, response SLAs, and first post-occupancy review date.
Attachments
Files attached here also appear in Project Documents.
Issue owner turnover package
Sam Rivera · Jul 22, 2026 to Aug 1, 2026 · 14 hrs
Depends on: Close Level 12 punch list, Secure final elevator certification
Package includes certificates, training records, O&M manuals, attic stock, and open-item log.
Attachments
Files attached here also appear in Project Documents.
Close Level 12 punch list
Noah Kim · Jul 12, 2026 to Jul 19, 2026 · 32 hrs
Depends on: Complete Level 12 owner quality walk
Daily trade huddles are focused on life-safety, finish, and access-control observations.
Attachments
Files attached here also appear in Project Documents.
Complete Level 12 owner quality walk
Daniel Brooks · Jul 5, 2026 to Jul 11, 2026 · 8 hrs
Owner walk is complete and 46 observations were logged by trade and unit.
Attachments
Files attached here also appear in Project Documents.
Secure final elevator certification
Rita Alvarez · Jun 30, 2026 to Jul 23, 2026 · 10 hrs
Retest is scheduled after the door-operator adjustment and emergency phone verification.
Attachments
Files attached here also appear in Project Documents.
Risks and issues
Elevator certification retest may delay owner turnover
Owner: Rita Alvarez
Close retest prerequisites and hold the inspector appointment with daily vendor confirmation.
Landscaping replacement may extend beyond turnover
Owner: Noah Kim
Complete life-safety access now and schedule final planting in the approved seasonal window.